The new build project is progressing well and, despite the delay in some activities such as roofing and external and internal painting due to poor weather conditions, the contractors still report a completion date of 21st July 2008.

Once the building is handed over to Kerrygold it is anticipated that there will be a three month period during which equipment transfer will take place. As you will have seen, the external aspects of the build are really taking shape with the current glazing of the main offices (shown in the photo above), the fitting of air handling units within the roof space, further drainage work and the ground works around the loading docks.



 
 

Internally, the contractors are laying concrete floor slabs within the reception and ground floor amenities area (i.e. offices, meeting rooms, locker rooms, toilets and canteen), ceilings are being fitted within the Bulk Cheese Store and the installation of plant and services continues with the fitting of pipe-work and cable containment.

 

 

 

 

 

 

 
home | why work with us | register online | community links | kerrygold news | kerrygold news archive | location map
other kerrygold websites: kerrygold uk | kerrygold family games | kerrygold recipes