Work is continuing preparing the foundation piles across the site, despite some recent disruption caused by an underground structure that was found around the area of a small basement we had previously discovered.

After excavating the area we found the structure to be an Old Water Filtration Tank covering an area of approx. 2000m3. This structure is now being removed along with the basement, which will enable the hole to be filled and the foundation piling to continue in this area.

The pile cap reinforced cages have been fitted and concreted in place around the footprint of the new Intake and Bulk Cheese Store, further spot piling continues around the same area.



 
 

Steel Work
Starting on the 10th September the first steels will arrive on site for the first area of construction:
the Bulk Cheese Store. The construction of the main structural frames will then continue into November.

Considering the recent issues we still remain optimistic that the project will remain close to plan and be ready for occupancy at the end of July 2008.



 

 